Brickell Bay Drive’s waterfront has been the subject of years of planning, community discussion, and resilience studies. Now, as the City moves toward construction, residents need a clear picture of what is changing and how it will affect their neighborhood.

The Brickell Bay Drive Seawall & Resiliency Improvements project combines shoreline protection with a renewed Baywalk, roadway work, drainage improvements, and landscaping. It covers the waterfront between SE 14th Street and SE 15th Road.

WHERE THE PROJECT STANDS

The City’s November 2026 update reports that 60% structural plans were approved with notes on November 9, with 90% structural plans expected in December. Construction is currently estimated for March 2027 through November 2028. These dates remain subject to change.

Read the City’s project update

THE LONG VIEW

Years in the making.

The project’s roots reach back to the years following Hurricane Irma. In September 2017, storm surge overtopped the aging seawall, highlighting the need for stronger shoreline protection.

The City’s Miami Forever Bond project list, approved December 13, 2018, allocated $1 million for the Brickell Bay Drive Design Criteria Package, covering seawall reconstruction and a linear park. Then-Commissioner Ken Russell’s District 2 office also described the planning and design funding in its December 2018 project overview. This was an early design allocation, separate from the full project’s construction budget.

An August 2018 Resilience Accelerator workshop expanded the vision to consider public access, green space, the environment, and neighborhood connectivity alongside flood protection. Resilient305 later described Brickell Bay Drive as a demonstration project that could inform waterfront standards elsewhere in Miami.

Irma exposes the vulnerability

Storm surge overtops the waterfront barrier along Brickell Bay Drive.

A broader waterfront vision

The August Resilience Accelerator workshop expands the approach. In December, Ken Russell’s office describes $1 million for planning and design.

Design enters the capital plan

The City includes a funded design-criteria package covering seawall reconstruction and a linear park.

Residents help shape the project

A December 13 meeting at Simpson Park gathers input on the waterfront, roadway, drainage, and pedestrian connections.

Residents discussing the seawall project at the Simpson Park community meeting
Simpson Park community meeting · December 13, 2021. Photo supplied by BHA.

Designs return to the community

A March 19 meeting at Emerald at Brickell presents the design and renderings and gathers further feedback.

Residents at Emerald at Brickell watching a presentation of the waterfront design
Emerald at Brickell community meeting · March 19, 2024. Photo supplied by BHA.

A design-build agreement

The City Clerk’s records identify the agreement with Magnum Construction Management dated November 19.

CURRENT STAGE

Engineering advances

EXP announces its design role in March. The City reports progress on the structural plans in November.

Construction target

The City currently estimates construction from March 2027 to November 2028. This schedule may change.

Timeline sources are linked in the documents section below.

UNDERSTANDING THE DESIGN

How much higher
will the seawall be?

The publicly presented design calls for a seawall crest at 8.0 feet NAVD88. The City’s earlier survey information placed the existing crest at approximately 4.2 feet NAVD88. That is a difference of approximately 3.8 feet, or about 3 feet, 10 inches. EXP’s March 2026 announcement repeats those figures.

SEAWALL CREST ELEVATIONS Same surveying reference: NAVD88
Earlier crest
4.2 ft
Proposed crest
8.0 ft

Approximate increase: 3.8 feet

The eight-foot figure is an elevation, not the wall’s height above the walkway. NAVD88 is a surveying reference. What pedestrians see depends on the difference between the seawall crest and the finished walking surface.

Existing low concrete seawall with white posts and chains beside the Brickell Bay Drive walkway
Existing seawall and walkway shown in the City of Miami / Tetra Tech presentation, March 2024. Photograph date not specified. View the full existing-conditions slide.

Updated cross-sections should show the wall, Baywalk, road, and neighboring entrances together. Those drawings would make the effects on views, accessibility, and building connections much easier to understand.

City streetscape rendering showing the proposed sidewalk, roadway and landscaped strip
Roadway and streetscape concept · City of Miami / Tetra Tech, March 2024. View the original presentation slide.

In its March 10, 2026 project announcement, EXP describes a linear greenway for pedestrians and cyclists, roadway reconstruction, and drainage improvements. Its description includes a soil-cell system beneath the sidewalk intended to support drainage and tree growth. The waterfront, street, and drainage infrastructure need to work together.

FOR CONDOMINIUM COMMUNITIES

What does this mean
for private seawalls?

Miami adopted Ordinance No. 13980 on March 25, 2021, updating waterfront construction and maintenance provisions. The published City Code §29-89 sets a six-foot NAVD88 minimum for applicable shoreline protection outside the Miami River and its tributaries. Permit applications must also demonstrate the ability to raise improvements incrementally, including at least two feet above minimum elevations, through 2070.

The code provisions reviewed do not establish an automatic requirement for every neighboring condominium to match the City’s proposed eight-foot elevation simply because this public project is proceeding.

The code does establish circumstances that can require private improvements. An association’s responsibilities depend on its own property and work:

New construction and substantial improvements

Applicable elevation and design requirements can be triggered by new construction or substantial improvements to a property.

Substantial seawall repairs

The threshold includes repairs affecting at least 50% of a wall’s length, costing at least 50% of a replacement wall, or changing the elevation along at least 50% of its length. Compliance can be required along the property’s shoreline.

Maintenance and flooding violations

Under City Code §29-95, owners must maintain their shoreline protection and prevent tidal water from passing through or over their property onto neighboring property or public rights-of-way. Violations can require corrective work. The code’s definition of tidal waters excludes storm-surge extremes as the test for an existing structure’s maintenance compliance.

The code provides a variance process for certain site constraints and alternative protective designs. Approval is conditional and does not remove the responsibility to protect neighboring properties and public streets.

At the County level, Ordinance 25-73, approved July 1, 2025, separately revised seawall and bulkhead permitting procedures and processing requirements. It concerns permitting and should not be described as a blanket eight-foot seawall mandate for Brickell condos.

What boards should establish

Who owns the seawall, its current elevation and condition, whether planned repairs trigger the code, and how the City’s improvements will connect to the property. A building’s engineer and legal counsel should evaluate those facts with the City.

RESIDENTS CARE.

Their questions
need answers.

Residents care about how this project will affect their homes and daily lives. The City should be forthcoming with updated plans and supporting analyses, and consult directly with affected condominium associations before the next community meeting. Boards, residents, and their building professionals should have time to review the information and receive clear answers.

How will the raised seawall, Baywalk, and road connect to existing buildings?

The City should provide drawings showing existing and proposed elevations at each adjoining property, including entrances, driveways, sidewalks, and connections between public and private seawalls. It should review those connections with each affected association and explain how access, accessibility, and waterfront views will change.

How will rainwater leave existing buildings and low areas after construction?

Residents should be able to review the City’s drainage analysis and understand where rainfall will flow after construction. The City should show how raised roads, sidewalks, and the seawall affect drainage from existing buildings and low areas, identify the routes and outlets that will carry water away, and explain the analysis’s assumptions and limitations. It should share that analysis with affected condo boards and their engineers, consult with them, and address their questions before the next community meeting.

Will any condominium need to modify its seawall, drainage, or entrances?

The City should identify the properties that may need related work and meet with those associations before the community meeting. For any work it considers required, it should explain the scope, legal basis, timing, permits, and responsibility for costs. The materials reviewed for this article do not establish building-specific obligations.

How will residents reach their buildings during construction?

The City should share a phased construction and access plan showing street closures, parking changes, deliveries, emergency access, and safe pedestrian and accessible routes. It should coordinate building-specific arrangements with condo management and identify a project contact and a process for advance notice of disruptions.

Who will pay for the work and maintain the completed improvements?

The City should publish a funding breakdown identifying committed funds, any remaining gaps, and any costs it expects property owners to bear. It should identify who will maintain the seawall, Baywalk, landscaping, and drainage system, including where public and private responsibilities meet.

When will the City share updated plans and consult with affected condos?

Before the next community meeting, the City should publish the updated drawings, drainage analysis, and a clear comparison with the March 2024 presentation. It should give affected associations time to review the materials with their professionals and consult directly with them about property-specific concerns. The community meeting should then explain the changes, address outstanding questions, and show how feedback will inform the plans before construction.

After nearly a decade of discussion, residents should be able to see how this investment will protect the neighborhood and how it will function at their own front doors.

FOLLOW THE PUBLIC RECORD

Sources & documents

Information reviewed November 23, 2026. The renderings illustrate the March 2024 presentation; the latest stamped construction plans have not been reviewed.